Search

Harmony Energy Park

IN DEVELOPMENT

About Harmony Energy Park

Harmony Energy Park is a proposed powered data park in Harmony Township, Cass County, North Dakota. The project is currently in development, and Geronimo Power is engaging with local residents, township officials and community leaders before moving into formal permitting.

Project Snapshot

  • Size: The project is proposed on one section of land (640 acres) in Harmony Township and would include two main data center buildings and supporting infrastructure. The data center buildings will be located one mile from any occupied residence.

    Over 75% of the section is expected to remain green space. Less than 25% (about 160 acres) would hold the buildings, access roads, parking lots and other developed areas, which is less than 1% of the total land in the township.

    The final location of project components is subject to change following final engineering and design; however, all project components will continue to comply with applicable township setbacks and standards.

  • Location: The project is located in Harmony Township in Cass County, North Dakota.
     
  • Timeline: Construction must begin within four years after a conditional use permit is issued, unless an extension is granted by the Township. The anticipated construction period is approximately two to four years.

These FAQs address project-specific questions about Harmony Energy Park, including the proposed location, infrastructure, permitting, construction, environmental considerations, community benefits, and other local topics.

Project Purpose

Harmony Township was an energy hub long before Harmony Energy Park was proposed. The existing Bison Substation and 345 kV transmission lines, plus the long-planned additional transmission lines and extension of a natural gas pipeline, collectively support North Dakota’s power and economic development goals. We proposed Harmony Energy Park here because of this existing and planned infrastructure.

Environment

Everyday water use for restrooms, sinks, breakrooms, and other employee needs is expected to average about 15,000 gallons per day, with peak demand approaching 20,000 gallons per day, roughly equivalent to the water used by one commercial car wash. A water supply study indicated that up to approximately 50,000 gallons per day could be available for these everyday needs, meaning the project’s anticipated demand is well below the amount identified as available. For cooling, the project will use a closed-loop system that continuously recirculates the same fluid in a sealed network, similar to a car radiator. It does not require continuous water use during normal operations.

Water for the closed-loop cooling system is sourced from a qualified off-site supplier and trucked in for the initial fill prior to operations. It is not drawn from the rural water district or from a well.

The data center must meet all applicable state and federal air quality requirements. Any equipment that could generate emissions is subject to permitting, monitoring, and reporting requirements. The facility is expected to be powered by new generation resources, which may include renewable energy, battery storage, and/or natural gas. New generation facilities would be separately permitted and regulated. Emergency backup generators are also subject to emission limits and oversight by the North Dakota Department of Environmental Quality.

Energy and Electricity

The initial electrical service is expected to provide up to 540 MW of power to the project site, with the potential for future expansion subject to end-user demand and utility requirements.

The data center is expected to be powered by new generation resources, which may include renewable energy, battery storage, and/or natural gas. Ratepayers would be protected from the costs associated with serving the new data center through the utility’s large load tariff, which has been filed with and is currently under review by the North Dakota Public Service Commission. This tariff is designed to ensure that costs incurred to serve data centers are paid entirely by the data centers themselves, rather than by other customers.

Sound and Appearance

Under the township ordinance, data centers are limited to 45 dBA within 100 feet of an inhabited residence or community building. For comparison, the nearby Casselton soybean processing facility was permitted at 60 dBA during the day and 55 dBA at night.

The data center is expected to be a campus-style commercial facility. Current plans place the data center buildings at least one mile from inhabited residences or community buildings, and at least 500 feet from non-participating property lines and Township right-of-way. Potential design features include neutral exterior colors, materials selected to reduce visual contrast, a campus-style layout, and shielded, downward-directed lighting that meets Harmony Township zoning requirements.

Economic Impact

The project is expected to support up to 1,500 construction jobs over the approximately two-to-four-year construction period, and up to 150 permanent jobs once operational. Those workers are also expected to support local businesses, including hotels, restaurants, gas stations, construction suppliers, and other service providers in the area.

Harmony Energy Park is expected to support up to 150 permanent jobs once operational. Many of these careers can begin with an apprenticeship, certificate or degree, with programs in electrical technology, HVAC, IT and other skilled trades already available in the region. That means local students and residents could build careers in growing industries like technology and energy, right here at home. See the expected breakdown below.

What types of permanent jobs are expected?

The project is expected to generate significant local tax revenue, estimated at approximately $72 million over 20 years, or roughly $3 to $4 million annually, and approximately $100 million over the full life of the project. These revenues will be distributed among local taxing jurisdictions and can help support local services, infrastructure, schools, and other community priorities as determined by local governments.

  • Specific tax revenue to local schools: When combined with the Harmony Solar and Storage projects, the projects are projected to be 23% of Mapleton and Central Cass school districts’ combined tax base; which means that for every $1.00 the school boards may need to raise, the projects are projected to pay roughly 23 cents.

Public Participation

No. We do not sign non-disclosure agreements (NDAs) with public officials.

The local permitting process provides the opportunity for formal public input. Project updates will be shared through Geronimo Power’s project communications and community outreach efforts. Geronimo Power has attended township meetings, held information sessions, and engaged directly with residents and community leaders ahead of filing an application, and has established a local community advisory committee to help guide charitable giving and identify local priorities.

Built for Community. Designed for Tomorrow.

Bringing new jobs, long-term investment, and community-driven benefits to Cass County. Harmony Energy Park is designed to strengthen local economies, support public services, and create lasting opportunities for the region’s future. Geronimo Power is developing Harmony Energy Park with a focus on transparency, local input and long-term community value. 

As planning continues, Geronimo Power will continue gathering feedback from residents, township representatives and local leaders. Community questions and concerns, including water, noise, traffic, roads, stormwater, lighting and other potential impacts, will be addressed through project design, development and permitting.

Project Benefits

Have a question? We want to hear from you! Contact the Harmony Energy Park project team at [email protected].

Community-Focused Development

At Geronimo Power, we believe strong projects are built on strong community relationships. Explore the stories, videos, and local updates below to see how we’re connecting with neighbors, supporting local initiatives, and staying engaged in the communities surrounding Harmony Energy Park.

Neighborhood News

Videos

Learn More from Our Permitting Team

Harmony Energy Park Conditional Use Permit (CUP) Application

Filed with Harmony Township on September 15, 2026.

Downloadable Documents

Vote on What Community Investment and Vegetation You Would Like to See

Which Community Investment Would You Most Like to See?

What Type of Vegetation Would You Like Along the Edge of the Data Center?

Say Yes to Development and Community Benefits

Say No to a Moratorium

Join Our Local Advisory Committee

Geronimo Power is looking for a Casselton or Mapleton area resident to join our local advisory committee. As someone who knows the community and its needs, you’ll help guide Geronimo Power’s charitable giving and identify where our support can make the greatest impact for local people and organizations.

Committee members:

  • Share insight on local needs, concerns and opportunities
  • Help identify local organizations, initiatives and causes that could benefit from Geronimo Power’s charitable giving and community support
  • Provide input on community topics such as roads, local services, agriculture, schools, emergency services and other community matters
  • Share questions or concerns from neighbors and other community members
  • Attend occasional meetings, dinners or learning sessions

The goal of the local advisory committee is to help Geronimo Power listen, learn and make thoughtful decisions about how we can support the communities around our projects.

Interested?
Email the team at [email protected]

Data Center Forum Recap

Let’s Talk Harmony Energy Park

Have questions about the proposed Harmony Energy Park? Join members of the Geronimo Power team for coffee or connect with us during office hours.

Join us for breakfast

 

Breakfast and coffee are on us. Stop in whenever it works for you.

Thursday, Oct 8 | 7:00 – 9:00 a.m.
Muddy Boots
649 Knutson St Ste 100
Mapleton, ND 58059

Stop by our office
Casselton office
26 6th Avenue North
Casselton, ND 58012

 

Tuesdays | 5:00 – 6:00 p.m.
October 6

 

Wednesdays | 8:00 – 9:00 a.m.
October 7

Learn More About Data Center Laws in North Dakota

Related News

Ethics & Compliance Hotline

Geronimo Power is committed to conducting business with honesty, integrity, and respect. We expect our employees, third parties, and business partners to act ethically, uphold human rights throughout our operations, and speak up when concerns arise. To report a concern, please use one of the options below.

External/Alert Line Anonymous

Web: report.syntrio.com/geronimopower 

Phone: 888-869-7438

Petition Challenging the Proposed Harmony Township Development Moratorium

Harmony Township has proposed a 24-month zoning moratorium on the establishment, construction, expansion or approval of solar energy facilities, wind energy facilities, data centers, battery energy storage systems, electric transmission lines, and gas-fired electrical generation facilities. This action is contrary to economic opportunities and impedes private property rights.

This petition expresses opposition to the proposed moratorium and is intended for submission to the Harmony Township Board of Supervisors.

Sidney Nuese Full Res

Sidney Nuese

Senior Project Developer
Geronimo Power

Sidney Nuese is a Senior Project Developer supporting the Nobles County Data Center through the development of its associated wind projects—Plum Creek 1, Plum Creek 2, and Lime Creek. A lifelong resident of southwestern Minnesota, Sidney brings deep local knowledge and nearly a decade of wind development experience. Since joining Geronimo Power in 2016, she has advanced multiple utility-scale wind projects across the region, building strong relationships with landowners and guiding projects from early siting through key development milestones.
 
She holds a bachelor’s degree in Business Management from Southwest Minnesota State University. Sidney lives near Hendricks, Minnesota with her husband, Jason, and their four children. Outside of work, she enjoys golfing and spending time on the lake.
Marta_Lasch_PRINTSIZE

Marta Lasch

Permitting Lead
Geronimo Power

Marta Lasch is the Permitting Lead for the Nobles County Data Center, where she oversees environmental due diligence and land use permitting across local, state, and federal agencies. With nearly a decade of expertise working at the company, she has advanced over 1,600 MW of utility-scale wind, solar, and storage projects throughout the Midwest and Texas—550 MW of which are in Minnesota. Her work focuses on regulatory compliance, environmental risk mitigation, and coordinating with multiple agencies to advance major infrastructure projects.

Marta holds a B.S. in Geology from Iowa State University. Outside of work, she enjoys traveling and dancing with her husband, exploring state parks, gardening, and cheering on the Frost.

Feedback Form