Get the Facts About Harmony Energy Park
We’re at the start of the permitting process
On September 15, we submitted our Conditional Use Permit (CUP) application to Harmony Township. That’s Step 1 of 4. Nothing has been approved.
- Geronimo submits its application after consulting with township staff. ✔ We are here
- The Township Board accepts the application and sets a public hearing date. Residents are notified and can review the application materials.
- Community members share questions and comments with the Township Board and Geronimo Power.
- The Township Board reviews public input and whether the application meets township standards, then approves or denies the CUP.
Now is when we want to hear from you
We are proud to work in the open and we actively seek community feedback. Tell us what you want to see from our project. Contact us at [email protected].
We have time
The permitting process isn’t on a clock. There’s time to talk, listen and build community interests into the project before any decision is made.
Don’t let a moratorium end the conversation. Sign the petition.
We’re at Step 1. The steps meant to give you a voice are still ahead.
A moratorium doesn’t give you more say. It takes your say off the table. Keep the conversation going and keep Harmony’s future in Harmony’s hands.
👉 Sign the petition against the 24-month moratorium